Our state of the art Gantt chart


Post by helpdeskpro »

The calculation of the finish variance considers non-working days, unlike the MS project that excludes weekends and holidays. For example, the calendar days difference between the days 24/09/2024 to 15/08/2024 is 40

AS-IS.png
AS-IS.png (45.76 KiB) Viewed 402 times

But I want to exclude the weekends, so the finish variance would be 27.

TO-BE.png
TO-BE.png (21.96 KiB) Viewed 402 times

Is there a way to configure it so that it excludes those days and only considers workdays?


Post by arcady »

Here is a ticket for the bug: https://github.com/bryntum/support/issues/8902
Thank you for the report!