Hi, I wanna know if is it possible to connect a Time Range to a Task.
For example, when user updates the task start date OR end date, it should cause a update in the Time Range start date, commiting to the store and consequently being sent in Sync update.
All my time ranges have 0 duration, so it won`t affect the end date.
If not possible to do this automatically, what is the best approach to recalculate the new date for the Time Range and updating it to be sent in the Sync payload?
Basically, the Time Ranges will be the user's project milestone dates. The reason we chose Time Ranges is because Bryntum Milestones are not visible on the X-axis of the timeline dates, making it difficult to see the milestone dates.
This way, we want the Time Ranges to have some connection with the tasks.
Example: The "Ready-made foods" milestone has a link to the "Buy food" task. This milestone must end 1 day after the end of the "Buy food" task.
The question is, if I reschedule the "buy food" task, I need the milestone date to be changed as well.
Hi,
making it difficult to see the milestone dates.
How exactly it makes difficult to see dates? Maybe we will find better approach.
According to your solution, nothing automated to sync timeRanges and tasks. You only might track changes and update stores accordingly, as Tasnim recommended.
Lets say we have this gantt:
- milestone.png (66.77 KiB) Viewed 169 times
If I had hundreds of tasks, my milestone (circled in red) would not be visible in the entire schedule. But the time range (circled in orange), is visible thoughout my entire Y-axis, no matter how deep I navigate.