When I first enter the page, the date range on my right gantt graph is too long, and part of the task name on the left is invisible. How can this be adaptive
Support Forum
You need to configure initial https://bryntum.com/docs/gantt/api/Gantt/view/Gantt#config-viewPreset
In docs you will find the list of pre-defined presets, you also can use your own setting or customize one of pre-defined
viewPreset : {
base : 'hourAndDay',
id : 'myHourAndDayPreset',
headers : [
{
unit : "hour",
increment : 12,
renderer : (startDate, endDate, headerConfig, cellIdx) => {
return "";
}
}
]
}
https://bryntum.com/docs/gantt/api/Scheduler/preset/ViewPreset
https://bryntum.com/docs/gantt/api/Scheduler/preset/PresetManager
All the best,
Alex
You can run my code, the gantt diagram on the right doesn't show up when I initialize it
- Attachments
-
- advanced1.0.7z
- (109.55 KiB) Downloaded 44 times
What I mean is that when the page is initialized, the task is not displayed on the gantt chart on the right, so you have to click Zoom to fit to see it. I hope that when I enter the page, I can see that the gantt chart on the right starts one week before the task starts and ends one week after the task ends
Just use consistent data.
I see you set startDate/endDate for your timeAxis somewhere in 2019,
gantt.config.ts
startDate: '2019-01-12',
endDate: '2019-03-24',
but according to your tasks data, your project starts in 2022. I also don't see you set start/end date for your project, so it will be calculated automatically according to data. If you will display correct date range of timeAxis, you will see tasks.
https://bryntum.com/docs/gantt/api/Gantt/model/ProjectModel#field-startDate
https://bryntum.com/docs/gantt/api/Gantt/view/Gantt#config-startDate
Docs about tasks scheduling: https://bryntum.com/docs/gantt/guide/engine/gantt_events_scheduling
All the best,