Post by visiniaga »

how to setup project end and duration, in the latest demo https://odoo-gantt.bryntum.com/web#cids=1&menu_id=109&action=175&active_id=4&model=project.task&view_type=BryntumGantt

there project Launch SaaS Product (Bryntum Gantt Pro), it show duration and project end, but cannot find where to configure it


Post by Terence »

You can only set startdate in the project settings forum. The enddate of the project is determined by its subtasks.


Post by visiniaga »

in the demo database,
while task have been added, project end wont update

Attachments
Screenshot 2022-08-03 22.19.38.png
Screenshot 2022-08-03 22.19.38.png (128.19 KiB) Viewed 803 times

Post by Terence »

You can set autoscheduling to true in the project settings or globally for all projects in the configuration panel. Then it will calculate the enddate.