The problem of data synchronization modification between Gantt view and odoo native task page

Posted: Tue Oct 12, 2021 2:47 pm
by admin@anviz.com

The executor of the Pilotrun task in the Gantt view is Angela Zhang, but the executor of the Pilotrun task in the odoo native project management project card is still the Administrator, and the changes are not synchronized. How to set their association? thanks


Re: The problem of data synchronization modification between Gantt view and odoo native task page

Posted: Tue Oct 12, 2021 4:46 pm
by Terence

We use a dedicated field to store and read the assignments which are all assigned in the Gantt Pro View. I guess you expect another field to be used as assignment source. We could actually consider other fields as assignment source and maybe add those.

But I am not sure (have no idea) what this field is or means and where (which model) it is coming from.

Screenshot 2021-10-12 at 16.38.51.png
Screenshot 2021-10-12 at 16.38.51.png (6.06 KiB) Viewed 1546 times

Could you clarify? Thank you in advance.


Re: The problem of data synchronization modification between Gantt view and odoo native task page

Posted: Thu Oct 14, 2021 3:05 am
by admin@anviz.com

We need to assign tasks in the Gantt view, and then the executor of the task will see his tasks in the project, and this function needs to be displayed in the task card in the screenshot above before it can be pushed to the system User interface, otherwise there are more tasks and each one needs to be processed. What I need is that the data of the Gantt view can be associated with the native fields of odoo


Re: The problem of data synchronization modification between Gantt view and odoo native task page

Posted: Thu Oct 14, 2021 10:28 am
by Terence

I have created a ticket to investigate this. It should be possible to synchronize the assignments. Put it on the list.

https://github.com/bryntum/odoo-support/issues/48