Is it possible to make a dependencie from a task with a task that starts before the end of the first task?

Ex. : task A from 02/01/2021 - 02/30/2021
task B from 02/10/2021 - 03/15/2021
How to have a demendencie between task A and task B?

Thank you


Post by mats »


Post by erwan »

Works. Thank you.