[ANGULAR] Resource Assignment Dates

Posted: Fri Jan 15, 2021 10:43 am
by rahulranjan

Hi
When i assign multiple resources on single task .

  • how do i know the start and end date for each of assigned resources ?
    how do i know which of the resource assignment is driving the task end date ?


Re: [ANGULAR] Resource Assignment Dates

Posted: Fri Jan 15, 2021 12:55 pm
by pmiklashevich

Assignments have no start/end dates. Only tasks have. Depending on the mode and assignments the task start/end date is calculated. Please read the guide to see how tasks are scheduled https://www.bryntum.com/docs/gantt/#engine/gantt_events_scheduling.md