Our state of the art Gantt chart


Post by Bhava »

Hi,
I want to create a new tooltip for the resource non working hours . I have attached the picture of the tooltip. the red color is the non working hours.

How should I proceed ?

Attachments
tooltip.png
tooltip.png (16.66 KiB) Viewed 263 times

Post by mats »

Sorry, it’s not quite clear what you mean. Please describe in greater detail what you are looking for


Post by Bhava »

I want to change tooltip of the picture I have shared
https://www.bryntum.com/examples/scheduler-pro/resource-non-working-time/

Attachments
tooltip.png
tooltip.png (93.5 KiB) Viewed 261 times

Post by alex.l »

Hi Bhava,

Not supported now, we have a feature request to add this feature here: https://github.com/bryntum/support/issues/1069
It also has a workaround in description.

All the best,
Alex